| | | | Mcintyre Square - June 2011 Updates - 6/2011: Primer is being applied to interior walls of Building A. Curb and gutters are being prepared for new asphalt in front of Building B. Building C is complete, is waiting for completion of the parking lot improvements. Building D is nearing completion. Building E exterior has been completed. The stucco application is being completed and the Storefronts are being installed for Building F. Building G is complete and future tenant County Club Animal Hospital has submitted plans. Buildings H and I are being prepared for the application of stucco.