The City of West Covina purchased the three "Coastal Sage Scrub/Golf Course" assets located at the BKK Landfill site (134-acres) and the rights to the area on the top deck that is under license (84.27-acres) from the Successor Agency to the Redevelopment Agency in August of 2018. 

In March of 2019, the City released a Request for Proposals (RFP) for development proposals for the sale of the City parcels and sub-license of the Top Deck. The City received four proposals and selected the proposal submitted by Singpoli Group, LLC. 

At this time the City is working with Singpoli Group, LLC towards the sale of the City parcels as well as the assignment of the license rights of the Top Deck for the development of the proposed public park with an amphitheater, horse/hiking trails, glamping campsite, habitat preservation and restoration, solar and greenhouse program, zipline and aerial adventure park, future virtual reality (VR) park, K-9 and Fire training facilities, and a resort hotel with banquet facilities.  

For additional information please visit the following pages:

  • Sportsplex Projects Overview                       - History of the Sportsplex Project (Site)
  • Request For Proposals (RFP)                        - Timeline & Proposals submitted
  • Executed Documents                                    - Documents executed pertaining to selection of Singpoli proposal
  • Previous Singpoli Proposals                         - Review previously submitted proposals from Singpoli
  • FAQ                                                                 - Submit questions regarding the site or proposed project

 



Development Opportunity Site Aerial

Icon-pdfClick here for pdf  

Development Opportunity Site

 


Singpoli Proposed Site Plan

Icon-pdfClick here for the PDF

Development Opportunity Site


Timeline

Milestone

Timeline

Execution of Purchase & Sale Agreement & Joint Escrow Instructions

August 1, 2019

Deposit of Escrow

Within 3 days from Opening of Escrow

Submittal of Project to City

(Zone change & General Plan change to update to a new Specific Plan)

TBD

City to retain CEQA consultant

Initiation of environmental review for CEQA; Commence Formal review of project by Regulatory Agencies

Approximately 2-3 months from submittal  to City

City to Complete preparation of requisite CEQA Review in accordance with applicable laws and regulations

Approximately 18 months from retention of consultant

Negotiation of Development Agreement

90-days prior to completion of CEQA review

Planning Commission Meeting

For consideration of Zone Change, recommendation of Development Agreement and CEQA document to City Council

Within 60-days of completion of CEQA noticing period and responses to questions

City Council Meeting

For consideration of Zone Change, CEQA document, Development Agreement, and approval to Close Escrow

Within 45-days of Planning Commission Approval

 *The dates are tentative and subject to change.

 

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer